EGEE II deliverables and milestones
list can be found
here.
Nature
= R = Report P = Prototype D = Demonstrator O = Other
M=Due Month. At maximum the last working day of the due month, the deliverable should be
sent to the moderator in order to start the formal review process.
Q1
M |
id |
Item |
Lead
Partner |
Nature |
Moderator/Reviewer |
Status |
| 1 |
DNA2.1 |
Production of Project
Information Presentation |
TERENA |
R |
M:SA1(
I. Bird)
R: NA1(B. Jones), NA3( J. Murison), NA4(F. Harris) |
Review starts:
10/05/04
PEB Approval: 27/05/04
Sent to EU: 28/05/04 |
| 1 |
DNA2.2.1
MNA2.1.1 |
External customer
facing web site, mailing lists and web based tools |
TERENA |
P |
M:
(JRA2)G. Zaquine
R: NA1(M-E Begin), NA3(J. Murison) , NA4(R.
Barbera) |
Review starts:
10/05/04
PEB decision-27/05/04: will be sent to Brussels by 28/05/04 and the
points raised during the review will continue to be addressed. |
| 1 |
DNA2.3.1
MNA2.2.1 |
Internal project
facing web site, mailing lists and web based tools |
CERN |
P |
M:
JRA2(G. Zaquine)
R: NA2(J. Dyer), SA1(R. Rumler), JRA1(E. Laure) |
Review starts:
10/05/04
PEB decision-27/05/04: will be sent to Brussels by 28/05/04 and the
points raised during the review will continue to be addressed. |
| 1 |
MNA4.1 |
Definition of requirements from
applications and first version of associated testsuite |
CNRS |
|
M: NA1(M-E Begin) |
The requirements part has been achieved. The test plan &
testsuite part will be ready during the second quarter.
Recommended
for acceptance (08/11/04). |
| 3 |
DJRA1.1 including
Release Plan |
Architecture and
Planning (Release 1) including JRA1 Release Plan |
CERN |
R |
M:
NA4(C. Loomis)
R: JRA3(J. Hahkala), JRA4(J.Orellana), SA1(M.Schulz,
A. Ferraro) |
Review starts:
01/07/04
PEB Approval: 22/07/04 |
| 3 |
MJRA1.1 |
Tools for middleware engineering and
integration deployed |
CERN |
P |
. |
Successfully completed by M3. |
| 3 |
MJRA1.2 |
Software cluster development and testing
infrastructure available |
CERN |
P |
. |
Successfully completed by M3. |
| 3 |
DNA1.1.1 |
First Quarterly
periodic report |
CERN |
R |
Reviewed internally |
. |
| 3 |
DNA1.2 |
Gender Action Plan |
CERN |
R |
M:
NA3(M. Atkinson)
R: NA2(John Dyer), SA1(A.Mills), JRA4(S. Nicoud) |
Review starts:
09/07/04
PEB Approval: 15/07/04 |
| 3 |
DNA2.4.1
MNA2.3.1 |
Dissemination Plan
with revisions at M9, and M15 including a formal planning for using
and disseminating knowledge throughout the project (including target
audiences and measures for success) |
TERENA |
R |
M:JRA1(E.
Laure)
R: NA1(B.Jones), NA3(M.Gronager), NA4(Y. Legre) |
Review starts:
01/07/04
PEB approval: 15/07/04 |
| 3 |
DNA3.1.1
MNA3.1 |
Training Plan with revisions at M9 and M15 |
UEDIN |
R |
M: NA2(L. Florio)
R: JRA1(M. Real), NA4(V. Breton), SA1(O. Prnjat) |
Review starts: 07/07/04
PEB approval: 15/07/04 |
| 3 |
DNA4.1 |
Definition of Common Application Interface
and Planning Document |
CNRS |
R |
M: NA1(B. Jones)
R: JRA1(S. Fisher), JRA3(M.Steenbakkers), JRA4(A.Patil) |
Review starts: 01/07/04
PEB approval: 15/07/04 |
| 3 |
DSA1.1 |
Detailed execution plan for first 15 months
of infrastructure operation |
CERN |
R |
M: SA2 (JP. Gautier)
R: NA1(M-E Begin), JRA1(L.Matyska, NA4(E. Fede) |
Review starts: 02/07/04
PEB approval: 15/07/04 |
| 3 |
MSA2.1 |
First meeting of EGEE-GEANT/NRENs Liaison Board. |
CNRS |
. |
. |
Done M3: http://agenda.cern.ch/
fullAgenda.php?ida=a042575 |
| 3 |
MJRA3.1 |
Completed user requirements survey defines effort
redistribution over action lines |
KTH/PDC |
. |
. |
First requirements
and
Requirements follow-up:
https://edms.cern.ch/document/485295/1
Done. |
| 3 |
MJRA3.2
|
Set-up of the PMA for European CAs and liaison with the
non-European ones |
KTH/PDC |
. |
. |
Done. |
| 3 |
MJRA4.1 |
Definition of initial network performance metrics and
composite measurements required. |
UCL |
. |
. |
The final version (v1.3) of the milestone has
been uploaded to EDMS. PEB approved. |
Q2
M |
id |
Item |
Lead
Partner |
Nature |
Moderator/Reviewer |
Status |
| 4 |
DJRA2.1
including
Measurement Plan |
Quality Plan for EGEE |
CSSI |
R |
M: NA1(M-E Begin)
R: SA1(A. Mills), JRA1(S.Beco), NA4(V.Breton). |
Review started: 02/08/04
First round review documents updated: 03/09/04; Sent to EU: 19/09/04 |
| 4 |
MJRA3.3 |
OGSA SEC service initial recommendations for reengineering |
KTH/PDC |
. |
R: JRA1(A.Fronher) |
Ready to be reviewed: 02/08/04
Reviewed - 19/08/04 : Recommended to be accepted- Accepted by PEB 23/09/04 |
| 4 |
DNA5.1.1 |
eInfrastructure reflection group White
Papers in conjunction with the EGEE Project Conferences |
CERN |
R |
M: NA3(R.Berlich)
R: SA1, NA4-JRA2(M. Soberman), SA2(M.Goutelle) |
A version of the white paper has
already been written and distributed to the eInfrastructure Reflection
Group (eIRG) organised by the EU. Sent to EU: 15/09/04 |
| 5 |
DJRA1.2 |
Design of grid services (Release 1) |
CERN |
R |
M: NA3(M.Atkinson)
R: SA1(C. Vistoli + Z.Sekeda), JRA3(P.Guio, D. Kelsey), NA4(R.
Météry + M. Lamanna) |
Review started: 01/09/04. Recommended
to be accepted by the PEB: 29/09/04. Accepted by the PEB 30/09/04. |
| 5 |
MJRA1.3 |
Integration
and testing infrastructure in place including
test plans (Release 1) |
CERN |
. |
R: NA1(M-E Begin) |
06/09/04: Reviewer report as recommended to be accepted - Accepted by the
PEB 23/09/04. |
| 5 |
MJRA2.1 |
Internal QA website deployed |
CSSI |
. |
M: NA3(R. Hopkins) |
Ready to be reviewed: 01/09/04
Recommended to be accepted by the PEB: 29/09/04. Accepted by the PEB 30/09/04. |
| 5 |
DJRA3.1 |
Global security architecture |
KTH |
R |
M: SA1(R.Cecchini)
R: JRA1(D.Kouril), JRA4(J. Ornella), NA4(J. Montagnat), JRA3(D.
Kelsey) |
Review started 01/09/04.
Recommended to be
accepted by the PEB: 01/10/04. Accepted by the PEB 07/10/04. |
| 6 |
MJRA3.4 |
Security operational procedures and incident handling, definition of a
common Grid incident format |
KTH/PDC |
. |
R: SA1(I.Neilson) |
Review
ongoing. Recommended
to be accepted by the PEB: 22/10/04.
PEB approval: 11/11/04. Sent to EU 15/11/04. |
| 6 |
DJRA4.1 |
Specification of interfaces for bandwidth
reservation services |
UCL |
R |
M: SA1(Jules Wolfrat)
R: SA2(Michael Boyarsky), JRA1(T. Ferrari), JRA3(D. Groep) |
TOC sent and agreed by
PEB. Review started 30/09/04. Recommended
to be accepted by the PEB: 05/11/04.
PEB approval: 11/11/04. Sent to EU 15/11/04. |
| 6 |
MJRA4.2 |
Requirements and use cases for monitoring and diagnostics tools for users,
middleware and operations |
UCL |
. |
R: SA1(F. Donno) |
This milestone has been combined with the SA2 DSA2.1 deliverable as
common SA2-JRA4 "Requirement and use cases". This document will be an
accompanying document of DSA2.1.
|
| 6 |
DNA1.1.2 |
Quarterly periodic report |
CERN |
R |
. |
. |
| 6 |
DNA2.2.2
MNA2.1.2 |
External web site and tools at full capacity |
TERENA |
P |
M: NA4(Y. Legre)
R: NA1(B.Jones), NA3(Richard Hopkins), NA5(H.Hammerle) |
TOC sent as well as status
of implementation of feedbacks from the DNA2.2.1 review. Review started 28/09/04 ,
first round completed. Second round comments, sent 01/11/04. Recommended to be accepted by the PEB: 10/11/04.
PEB approval: 11/11/04. Sent to EU 15/11/04. |
| 6 |
DNA2.3.2
MNA2.2.2 |
Internal web site and tools at full capacity |
CERN |
P |
M: JRA4(Maarten Buchli)
R: NA4(Y. Legre), JRA2(G. Romier) |
TOC sent and agreed by PEB. Review started 28/09/04. Recommended
to be accepted by the PEB: 13/10/04.
PEB approval: 11/11/04. Sent to EU 15/11/04. |
| 6 |
DNA2.5
MNA2.4 |
Production of appropriate printed PR
material |
CERN and TERENA |
R |
M: NA5(A.Fuentes)
R: NA3(David Horn), JRA2(E. Sanchez) |
TOC sent and agreed by PEB. Review started
28/09/04. First round comments sent 03/11/04. Review completed. Recommended
to be accepted by the PEB: 10/11/04. PEB approval: 11/11/04. Sent to EU 15/11/04. |
| 6 |
DNA2.6.1
MNA2.5.1 |
Dissemination Progress Reports with
revisions at M12 and M18 |
TERENA |
R |
M: NA1(Rosi Mondardini)
R: NA3(Elena
Slabospitskaya), NA5(M.Heikkurinen) |
TOC sent and agreed according PEB
comments. Review started 06/10/04. Recommended
to be accepted by the PEB: 01/11/04. PEB approval: 11/11/04. Sent to EU 15/11/04. |
| 6 |
DNA3.2
MNA3.2 |
Initial Training Course Material
(continuously revised thereafter) |
UEDIN |
R |
M: NA2(Licia Florio)
R: NA4(Roberto Barbera),
SA1(Per Oster ) |
TOC
sent-29/09/04 and agreed. Review started 12/10/04. First round feedback sent by 26/10/04. Recommended
to be accepted by the PEB: 08/11/04. PEB approval: 11/11/04. Sent to EU 15/11/04. |
| 6 |
DNA4.2
MNA4.2 |
Target Application Sector Strategy document |
CNRS |
R |
M: NA1(Bob Jones)
R: NA2(J.Dyer), NA3(Ladislav Hluchý), JRA1(E. Laure, J.Flammer),
SA1(Horst Schwichtenberg) |
TOC sent and agreed by the PEB. Review started 04/10/04. First round feedback sent by 19/10/04. Recommended to be accepted by the PEB: 11/11/04. PEB approval:
11/11/04. Sent to EU 15/11/04. |
| 6 |
DSA1.2
MSA1.1 |
Release notes corresponding to the initial
pilot Grid infrastructure operational |
INFN |
R |
M: JRA2(G.Zaquine)
R: NA3(David Fergusson), NA4(Frank Harris); NA1(Bob Jones) |
TOC sent; QA items as agreed between Ian and Bob are provided
separately. Review
started 08/10/04. First round feedback sent by 15/10/04. Second round version sent 29/10/04. second
round comments sent 07/11/04. Recommended
to be accepted by the PEB: 10/11/04. PEB approval: 11/11/04. Sent to EU 15/11/04. |
| 6 |
DSA2.1 |
Survey of application requirements and
identification of service classes. |
CNRS |
R |
M: JRA3(G.Venekamp)
R: NA4(Genevieve
Romier and Julia Andreeva), SA1(Robin Tasker) |
TOC sent and agreed by
PEB. Review started 01/10/04. Review completed. Recommended to
be accepted by the PEB: 03/11/04. PEB approval: 11/11/04. Sent to EU 15/11/04. |
Q3
M |
id |
Item |
Lead
Partner |
Nature |
Moderator/Reviewer |
Status |
| 9 |
MNA1.1 |
Successful completion of first review |
CERN |
. |
M: NA1 |
. |
| 9 |
DNA1.1.3 |
Quarterly periodic report |
CERN |
R |
M: NA1 |
. |
| 9 |
DNA1.3.1 |
Periodical report |
CERN |
R |
M: NA1 |
. |
| 9 |
DNA2.4.2
MNA2.3.2 |
Dissemination Plan revision including a
formal planning for using and disseminating knowledge throughout the project (including
target audiences and measures for success) |
TERENA |
R |
M:JRA1(E. Laure)
R: NA1(B.Jones), NA3(M.Gronager), NA4(Y.Legre) |
Scope accepted
(02/12/04). Review started 10/12/04. Fist round review completed on Dec. 15. Third round
underway. Review completed. Recommended
to be accepted by the PEB: 12/01/05. Approved by the PEB 20/01/05 and sent to the EU. |
| 9 |
DNA3.1.2 |
Training Plan revision |
UEDIN |
R |
M: NA2(Licia Florio)
R: JRA1(M. Real), NA4(G.Andronico), SA1(.O. Prnjat) |
TOC accepted (02/12/04) Review
started 14/12/04. Review completed. Recommended
to be accepted by the PEB: 12/01/05. Approved by the PEB 20/01/05 and sent to the EU. |
| 9 |
DNA3.3.1 |
Training Progress Report with updates at M15
and M24 |
UEDIN |
R |
M: JRA1(Steve Fisher)
R: NA4(Roberto Barbera),
SA1(Per Oster ), NA2(Licia
Florio) |
TOC accepted (02/12/04). Review
started 10/12/04. Second round underway. Review completed. Recommended
to be accepted by the PEB: 10/01/05. Approved by the PEB 20/01/05 and sent to the EU. |
| 9 |
DNA4.3.1 |
EGEE Application Migration Progress report
with revisions at M15 and M21 |
CNRS |
R |
M: NA1(Marc-Elian)
R: NA2(J.Dyer), NA3(Ladislav Hluchý), SA1(Horst Schwichtenberg) |
TOC
accepted (02/12/04). Review started 13/12/04. Second round underway. Review completed.
Review completed. Recommended
to be accepted by the PEB. Approved by the PEB 20/01/05 and sent to the EU. |
| 9 |
DNA5.1.2
MNA5.1 |
eInfrastructure reflection group White
Papers in conjunction with the EGEE Project Conferences |
CERN |
R |
|
TOC accepted (02/12/04). White
paper itself will be sent out as an EGEE deliverable but it will not be reviewed. |
| 9 |
DNA5.2 |
European Grid project synergy roadmap (in
collaboration with DEISA, SEE-GRID and other relevant initiatives and EU projects) |
CERN |
R |
M: NA3(David
Fergusson)
R: SA1(Ian Bird), NA4-JRA2(M. Soberman), SA2(M.Goutelle) |
TOC accepted (02/12/04). Review started
13/12/04. Second round underway. Review completed. Recommended
to be accepted by the PEB: 11/01/05. Approved by the PEB 20/01/05 and sent to the EU. |
| 9 |
DSA1.3 |
Accounting and reporting web site publicly
available |
CCRLC |
R |
M: JRA1(M.Barroso)
R: JRA2(Genevieve
Romier), JRA3(Yuri Demchenko), NA4(José R. Valverde) |
TOC accepted (02/12/04).
Review started 13/12/04. Second round underway. Review completed. Recommended
to be accepted by the PEB: 12/01/05. Approved by the PEB 20/01/05 and sent to the EU. |
| 9 |
MSA2.2 |
Initial requirements aggregation model, specification of services as SLSs
on the networks |
CNRS |
. |
M:SA1(Ian Bird) |
TOC
accepted (02/12/04 ) with some possible further comments from Eike Jessen. Review
started 14/12/04. First round review comments sent by 29/12/04. Second round underway.
Review completed. |
| 9 |
MJRA1.4 |
Software for the Release Candidate 1 |
CERN |
. |
M: SA1(Zdenek
Sekera)/NA4(Massimo Lamanna) |
TOC
accepted (02/12/04). Review started 16/12/04. One month late.
Under gLite management review committee decision. |
| 9 |
DJRA3.2 |
Site access control architecture |
FOM |
R |
M: JRA1(Massimo Sgaravatto)
R: SA1(Ian Neilson), NA4(christophe Blanchet, Ignacio Blanquer), NA3(Ludek Matyska) |
TOC.
Initial version of the deliverable has been submitted by 13/12. Second round
underway. Review completed. Recommended
to be accepted by the PEB: 11/01/05. This deliverable will be recommended by PEB pending
positive responses from SA1 and NA4 by the 18th Jan. Positive responses received from SA1
and NA4 by 18/01/05. Approved by the PEB 20/01/05 and sent to the EU. |
| 9 |
MJRA3.5 |
Secure Credential Storage procedures |
KTH/PDC |
. |
M: SA1(Ian Neilson) |
TOC
sent 02/11/04 and accepted. Split in 2 phases: Phase 1: deliver by PM10, collected information on currently
used secure credential storage solutions, as input to MJRA3.6. Very first version
sent by 16/12/04. New version sent by 20/01/05 to the moderator. Review
completed 07/02/05.
Phase 2: deliver final MJRA3.5 recommendation document by PM15 |
| 9 |
DJRA4.2 |
Definition of standardized network
measurement query/response interfaces |
UEDIN |
P+R |
M: JRA1(Tiziana Ferrari)
R: SA1(Nick Thackray), JRA2(Genevieve Romier) |
TOC accepted (02/12/04). Review started
10/12/04. First round review comments sent by 03/01/05.Review completed. Recommended
to be accepted by the PEB: 12/01/05. Approved by the PEB 20/01/05 and sent to the EU. |
A dedicated PEB meeting is organised on the 13th of January for the presentation
of the following M9 deliverables: DNA3.3.1, DNA4.3.1, DSA1.3, DJRA3.2
We
successfully passed the first project review. All deliverables are
accepted with
the exception of minor editing required to the periodic
report
DNA1.3.1
Q4
M |
id |
Item |
Lead
Partner |
Nature |
Moderator/Reviewer |
Status |
10 |
MJRA1.5 |
Integrated
Release Candidate 1 enters testing and validation period (Release 1) |
CERN |
. |
M:
gLite management review committee |
TOC
(24/02/05).
Accepted by the PEB (07/04/05). |
| 12 |
DJRA1.3 |
Software and associated documentation
(Release 1) |
CERN |
P+R |
M:
“gLite management review committee” +NA3(David
Fergusson) |
TOC (24/02/05).
Review started 05/04/05. PEB approval (28/04/05). |
| 12 |
DJRA2.2 |
Annual Report on EGEE Quality Status,
including software and Grid operations and plan for second year |
CSSI |
R |
M: NA1(Marc-Elian)
R: SA1(Phillipa
Strange), NA4(Eric
Fede), JRA1(Stefano
Beco) |
TOC
(18/02/05). Review started 04/04/05. PEB approval(28/04/05) |
|
12 |
MJRA3.6 |
Security
operational procedures (first revision) |
KTH/PDC |
. |
M:
Chairman of the Security. Group (David.Kelsey) |
TOC
(21/02/05). Review started(01/04/05).
Recommended to be accepted. PEB approval (12/05/05) |
|
12 |
MJRA3.7
|
Framework
for policy evaluation accepted in GridPMA policies and determination of the CA service
authorities for EGEE |
KTH/PDC |
. |
M:
Christos Kanellopoulos
(EUGridPMA.member) |
TOC
(18/02/05). Review started 30/03/05. Review completed.
Recommended to be accepted. PEB approval (12/05/05) |
12 |
MJRA4.3 |
Prototype tool to access network performance metrics from a limited set
of measurement points |
UEDIN |
. |
M:
JRA1(Tiziana Ferrari)+SA2(Mathieu Goutelle) |
TOC
(21/02/05). Review started 01/04/05. Review completed (22/04/03.
Recommended
to be accepted. PEB approval (12/05/05) |
| 12 |
DNA1.1.4 |
Quarterly periodic report |
CERN |
R |
. |
. |
| 12 |
DNA2.6.2
MNA2.5.2 |
Dissemination Progress Reports revision |
TERENA |
R |
M:
NA1(Bob Jones)
R: NA3(Dr
Anna Kenway), NA5(Antonio.Fuentes) |
TOC
(22/02/05). Review started 04/04/2005. review completed.
Recommended to be accepted. PEB approval (12/05/05) |
| 12 |
DSA1.4 |
Assessment of initial infrastructure
operation and plan for next 12 months |
CNRS
(IN2P3) |
R |
M:
NA4(Roberto Barbera)
R: NA3(Peter
Oettl ),
Kors Bos |
TOC
(22/02/05). Review started (01/04/05). PEB approval (28/04/05) |
12 |
MSA2.3 |
Operational
interface between EGEE and GEANT/NRENs. |
CNRS |
. |
M:
JRA4(Gloria
Vuagnin), JRA4(Anand
Patil) |
TOC(23/02/05).Review
started (04/04/05). Review completed.
Recommended to be accepted. PEB approval (12/05/05) |
| 12 |
DSA2.2 |
Institution of SLAs and appropriate policies |
CNRS |
R |
M:
SA1(Gabriel NEAGU),
R: JRA4(Anand
Patil), NA4(Genevieve Romier) |
TOC
(24/02/05). Review started (04/04/05). Review completed.
Recommended to be accepted. PEB approval (12/05/05) |
Q5
M |
id |
Item |
Lead
Partner |
Nature |
Moderator/Reviewer |
Status |
|
12->13 |
MNA3.3 |
First
external review of User Training and Induction with feedback |
UEDIN |
. |
R: NA4(Vincent
Breton,
Florence Jacq) |
TOC
(23/02/05).
Has been presented at AAM.
PEB approval 09/05/05 |
12->14 |
MNA4.3 |
First external review of Applications Identification and Support with
feedback |
CNRS |
. |
R: NA3(Malcolm
Atkinson) |
TOC
(24/02/05)
Has been presented at AAM.
Waiting Malcolm's feedback from the user
survey. |
| 14 |
DJRA1.4
& Planning |
Architecture and Planning (Release2) |
CERN |
R |
M: PTF(Cal
Loomis)
R: SA1(Zdenek
Sekera);
NA4(Massimo Lamanna); NA3(Sara
Collins) |
Ready for the review. Second round review on
going.
PEB approval 14/07/05 |
| 14 |
DSA1.6 |
Release notes corresponding to the full
production Grid infrastructure operational |
CCRLC |
R |
M: JRA2(G.Zaquine)
R: NA3(David Fergusson), NA4(Frank Harris);
NA4(Angel
Merino ) |
TOC
(10/05/05). Review started 03/06/05. Review
completed (27/06/05).
Recommended for PEB approval. PEB approval (01/07/05) |
|
14 |
MSA1.3 |
Full
production Grid infrastructure (20 Resource Centres) operational. |
CERN |
. |
M: JRA2(G.Zaquine)
|
Already achieved.
Should be mentioned in the QR5. |
| 15 |
DJRA1.5 |
Design of grid services (Release 2) |
CERN |
R |
M:
NA4(Massimo Lamanna)
R: SA1(C. Vistoli),
JRA3(Gerben
Venekamp), JPSG(D..Kelsey) |
TOC
see DJRA1.2.
Review will start by 07/07/05. Second round review be completed
by 04/08/05. PEB approval (04/08/05). |
| 15 |
DNA1.1.5 |
Quarterly periodic report |
CERN |
R |
. |
. |
| 9->15 |
MJRA3.5 |
Secure Credential Storage procedures |
KTH/PDC |
. |
M:
Chairman of the JPSG (David.Kelsey) |
Split in 2 phases: Phase 1: deliver by
PM10. Phase 2: deliver final MJRA3.5 recommendation document by PM15
TOC
(08/06/05).
Review started
(10/06/05).
Recommended to PEB (14/07/09). PEB approval (22/09/05). |
15 |
MJRA4.4 |
Prototype bandwidth reservation within static network configuration |
UEDIN |
. |
M:
SA2(Mathieu Goutelle)
R: SA2(Veniamin Konoplev); GRNET(Afrodite
Sevasti,
Costas Kotsokalis) |
TOC (19/05/05). Review started 01/07/05.
Second round ongoing.
Recommended (28/07/05). PEB approval (04/08/05). |
15 |
MJRA4.5 |
Specification of end-to-end bandwidth reservation system. |
UEDIN |
. |
M:
SA2(Mathieu Goutelle)
R: SA2(Veniamin Konoplev); GRNET(Afrodite
Sevasti,
Costas Kotsokalis) |
TOC (19/05/05). Review started 01/07/05. Second round
ongoing.
Recommended (28/07/05). PEB approval 04/08/05). |
| 15 |
DNA2.4.3
MNA2.3.3 |
Dissemination Plan revisions including a
formal planning for using and disseminating knowledge throughout the project (including
target audiences and measures for success) |
TERENA |
R |
M:
NA1(Bob Jones)
R: NA3(Dr
Anna Kenway), NA5(Dimitrios
Vergados) |
TOC
(19/05/05). Second round review started 04/07/05.
Review completed 19/07/05-
Recommended. PEB approval
04/08/05). |
| 15 |
DNA3.1.3 |
Training Plan revision |
UEDIN |
R |
M: JRA1(Steve Fisher)
R: NA4(Roberto Barbera),
SA1(Ognjen
Prnjat ),
NA2(Rosette
Vandenbroucke) |
TOC
from DNA3.1.2.
Review started by 07/07/05. Review
completed by 18/08/05. PEB approval (18/08/05). |
| 15 |
DNA3.3.2 |
Training Progress Report update |
UEDIN |
R |
M: JRA1(Steve Fisher)
R: NA4(Roberto Barbera),
SA1(Ognjen
Prnjat), NA2(Owen
Appleton) |
TOC
from DNA3.3.1.
Review started by 07/07/05. Review
completed by 18/08/05. PEB approval (18/08/05). |
| 15 |
DNA5.1.3 |
eInfrastructure Forum White Papers in
conjunction with the EGEE Project Conferences |
CERN |
R |
Reviewed by eIRG |
Sent
to EU 07/09/05. |
Face to face meeting by 3-4/10 for DJRA4.3,
DNA2.6.3, DNA4.3.2, DNA5.3-4
Q6
Q7
Q8
PM22 timeline: 01/02/06 review starts; 15/02/06 1st round completed;
28/02/06 review completed; 09/03/06 PEB/PMB approval; 14/03/06 sent to
EU
PM23 timeline: 01/03/06 review starts; 15/03/06 1st round completed;
31/03/06 review completed; 09/04/06 PEB/PMB approval; 14/04/06 sent to
EU
M |
id |
Item |
Lead
Partner |
Nature |
Moderator/Reviewer |
Status |
| 24->22 |
DSA2.3 |
Revised SLAs and policies |
CNRS |
R |
M:
SA1(Gabriel NEAGU),
R: JRA4(Anand
Patil), NA4(Genevieve Romier) |
TOC (17/12/05).
Review started (31/01/06).
Recommended to be accepted (23/02/06).
PEB approval 13/03/06 |
| 24->22 |
DJRA2.3 |
2nd Annual report on EGEE Quality Status,
including software and Grid operations |
CSSI |
R |
M: NA1(Marc-Elian)
R: SA1(Phillipa
Strange), NA4(Yannick
Legre), JRA1(Stefano
Beco) |
TOC(13/12/05).
Review started (03/02/06).
Recommended for PEB approval (09/03/06). PEB approval 09/03/06 |
| 24->22 |
DJRA3.4 |
Assessment of security infrastructure report |
KTH |
R |
M: SA1(I.Neilson)
S:
JRA1(Daniel
Kouril), NA4(Johan
Montagnat); |
TOC(12/12/05).
Review
started (18/02/06).
Recommended
for PEB approval (13/03/06). PEB approval 14/03/06 |
| 24->23 |
DJRA1.7 |
Final report on middleware re-engineering |
CERN |
R |
M: NA1(Erwin
Laure)
R: SA1(Mattias.Wadenstein);
NA4(Andrew
Maier &
Nicolas Jacq); NA3(David Fergusson) |
TOC (03/02/06).
Review started 28/02/06.
Recommended for PEB approval (05/03/06). PEB approval 06/04/06 |
| 24->23 |
DJRA4.6 |
Report on bandwidth allocation and
reservation |
UEDIN |
R |
M:
SA2(Mathieu Goutelle)
R: SA2(Veniamin Konoplev); GRNET(Afrodite
Sevasti,
Costas Kotsokalis) |
TOC(20/01/06).
Review started 28/02/06.
Recommended for PEB approval (24/03/06). PEB approval
30/03/06 |
| 24->23 |
DJRA4.7 |
Report on network monitoring |
UEDIN |
R |
M:
NA4(Charles.Loomis)
R: SA1(C.
Vistoli), JRA3(Gerben
Venekamp), JPSG(D..Kelsey) |
TOC(20/01/06).
Review started 06/03/06.
Recommended for PEB approval (24/03/06). PEB approval
30/03/06 |
| 24->23 |
MNA4.4 |
Second external review of Applications
Identification and Support with feedback |
CNRS |
. |
M:
NA2(Salva
Ilyin)
R: NA3 (?), but all the activities
should have a look at |
Ready for review(22/05/06).
Recommended to PEB(01/06/06) |
| 24->23 |
DNA4.4
combined with
DNA4.3.3 |
Final Report of Application Identification
and Support Activity with revision of EGEE
Application Migration Progress report |
CNRS |
R |
M:
JRA1(Steve
Fisher)
R: SA1(Alistair
Mills,
Einar Bjorgo,
Patricia Mendez,
Sean Moran);
NA2(Slava Ilyin);
NA3(David Fergusson);
JRA2(Marcel Soberman) |
TOC(09/02/06).
Review started 13/03/06.
Recommended for
PEB approval (03/04/06). PEB approval 06/04/06 |
| 24->23 |
DNA5.5 |
Final progress report on International
Cooperation Activities |
CERN |
R |
M: JRA1(Claudio
Grandi);
R:
NA3(David Fergusson); SA1(Jose R
Valverde); NA2(Hannelore Hammerle);
(the document should be sent to DEISA and See-Grid). |
TOC (06/02/06).
Review started 17/03/06.
Recommended for PEB approval (07/04/06). |
| 24->23 |
DSA1.8 |
Assessment of production infrastructure
operation |
CRNS
(IN2P3) |
R |
M:
NA3(Mike
Mineter)
R: JRA1(Ludek
Matyska);
NA4(Ignacio Blanquer);
JRA3(Yuri Demchenko); . |
TOC(09/02/06).
Review started 17/02/06.
Recommended for PEB approval (06/04/06). PEB approval 06/04/06 |
| 24 |
DNA1.1.8 |
Quarterly periodic report |
CERN |
R |
. |
. |
| 24 |
MNA1.3 |
Successful
completion of third and final review |
CERN |
. |
. |
. |
| 24 |
DNA1.3.2
Combined with DNA1.3 |
Periodical report.
|
CERN |
R |
. |
. |
|